Tool 04 · Whole journey

Redevelopment Timeline Planner

See a realistic month-by-month timeline for the whole project, with an honest buffer for the delays that almost always happen.

Timeline PlannerLive
% added to each stage
Feasibility & committee buy-in4 mo
PMC appointment & tender4 mo
Builder selection & negotiation5 mo
Development agreement & registration4 mo
Approvals (IOD / CC)7 mo
Vacating & demolition4 mo
Construction36 mo
OC, possession & conveyance5 mo
Planned total
69months
That's about
5.8years

Base durations are typical Maharashtra ranges. The buffer is the honest bit - projects with a 0% buffer are the ones that overrun.

What this calculator assumes

Builders typically present a single, optimistic construction timeline and leave out every stage that happens before the first foundation is poured, feasibility, PMC appointment, builder selection, the development agreement, and approvals can together take as long as construction itself, and rarely appear in a builder's pitch deck at all.

This planner lays out all eight stages of a typical redevelopment, from feasibility and committee buy-in through to OC, possession and conveyance, using base durations drawn from how Mumbai and Thane-area projects typically unfold. You can adjust any stage to reflect your own building's circumstances.

The total this produces is the number that should anchor your rent compensation negotiations, since every month of delay is a month of rent the builder owes you. Pair it with the Rent Compensation Estimator to see the real cost of an optimistic timeline slipping.

Editorial, not legal or financial advice. Consult your own advisors before deciding. This calculator is indicative and uses simplifying assumptions; confirm specifics for your project with your PMC and advisors. Nothing you enter here is stored or sent anywhere, it runs entirely in your browser.